Instrumentation Plan
Instrumentation for CC9 was installed in the P-152MR, P-154MR, P-209MR, P-401MR, and P-403MR pavement layers. No instrumentation was installed in the P-307MR Cement Treated Permeable Base layer. Moisture sensors were installed in the P-152MR subgrade layer only. Pressure cells and coil sensors were installed in all subgrade (P-152MR), subbase (P-154MR), and standard base (P-209MR) layers. Thermocouples and strain gauges were installed in asphalt layers (P-401MR and P-403MR) only. Gauge selection was based on reliability, accuracy, and ease of handling at the construction site. The tables below show the purpose of each sensor, and the types and quantity of each gauge along with the test areas they were placed in.
In addition to the five main sensor types, Smart Rocks and Bender Elements are experimental sensors that were installed by universities for research purposes in collaboration with the FAA. Smart rocks have corresponding antennas that were also installed in the pavement to improve the signal.
Sensor Data Recording and Purpose
(Click to Zoom)
Sensor Quantity
(Click to Zoom)
An overview of the CC9 instrumentation is shown below. For a PDF version of the CC9 As-Built Drawings click here.
CC9 Instrumentation Plan View (Click to Zoom)
CC9 Instrumentation Profile View - North Side (Click to Zoom)
CC9 Instrumentation Profile View - South Side (Click to Zoom)
Sensor Legend (Click to Zoom)
Pavement Legend (Click to Zoom)
For more information on the Instrumentation installed for each experiment click on the links in the table below.
Fatigue Model and Base Course Thickness Test Area
CC9 Fatigue Model and Base Course Thickness Instrumentation Plan View (Click to Zoom)
CC9 Fatigue Model and Base Couse Thickness Instrumentation Profile View - North Side (Click to Zoom)
CC9 Fatigue Model and Base Course Thickness Instrumentation Profile View - South Side (Click to Zoom)
Geosynthetics Test Area
CC9 Geosynthetics Instrumentation Plan View (Click to Zoom)
CC9 Geosynthetics Instrumentation Profile View - North Side (Click to Zoom)
CC9 Geosynthetics Instrumentation Profile View - South Side (Click to Zoom)
Cement Treated Permeable Base (CTPB) Test Area
CC9 CTPB Instrumentation Plan View (Click to Zoom)
CC9 CTPB Instrumentation Profile View - North Side (Click to Zoom)
CC9 CTPB Instrumentation Profile View - South Side (Click to Zoom)
Overload Test Area
CC9 Overload Instrumentation Plan View (Click to Zoom)
CC9 Overload Instrumentation Profile View - North Side (Click to Zoom)
CC9 Overload Instrumentation Profile View - South Side (Click to Zoom)