Daily Notes
During the duration of the CC1 Testing, daily trafficking notes were created. Daily notes were created to document the traffic testing within the NAPTF. The daily notes included general information regarding the testing parameters, loading conditions, completed passes, vehicle faults, instrumentation issues, and testing start and finish times.
To view the Daily Trafficking Notes for the CC1 Experiment click here.
The following timeline captures all activities performing during CC1:
April 1999 – NAPTF facility opened
May 1999 – CC1 test items construction completed
June 1999 – January 2000 – HWD deflection testing
August 1999 – September 1999 - Response testing: consisted of a series of static load, slow rolling and heavy weight deflectometer (HWD) testing
Feb 14, 2000 – Traffic testing began. After 28 passes, corner cracks occurred in MRS and HRS test items
March 3, 2000 – Static Response Tests performed on flexible pavement
March 30, 2000 – Traffic resumed and continued until all slabs were cracked
March 31, 2000 – HRS trafficking completed
April 6, 2000 – MRS trafficking completed
April 10, 2000 – LRS trafficking completed
May 2000 – High strength flexible test items trafficking completed after 5,000 passes
November 2000 – Trafficking stopped due to low ambient temperatures
May 2001 – trafficking resumed on flexible pavement
July 2001 – CC1 trafficking completed