CC7 South Painting Plan

The construction team developed a pavement marking plan to complete the construction of the CC-7 test area (see CC-7 Painting Plan).  The CC-7 test area was marked to identify the test items and identify locations for Non-Destructive Testing (NDT).  The markings provided the pavement engineers and researchers known locations for data collection and pavement monitoring during traffic testing. 

 

The painting contractor used a latex based paint and typical line striping equipment to complete the task.  The task was completed in July 2014.

 

Click here to download the CC7 Painting Plan.  On the drawing, the area from the centerline of the facility (0’ offset) and all the negative offsets to -33’ correspond to the Perpetual Pavement Test and the area from the centerline of the facility (0’ offset) and all the positive offsets to 33’ correspond to the Overload Test area.

 

Return to Construction Cycle 7 Overview